Three numbers frame the UK data centre market in late 2026. Savills records UK vacancy at 8% in the first quarter of 2026, down from 27% in 2016. CBRE forecasts London vacancy falling to 5.5% by the end of 2026, which would be an all-time low. And Savills says 96% of the c.66MW of capacity due to complete between the second and fourth quarters of 2026 is already pre-sold.
This review pulls together what the main market reports and this autumn’s news say about demand, supply, power, capital and consent. The short version is that demand and capital are not the constraint. Dates are. And since this autumn, public consent has joined power as a gating item.
Demand is outrunning supply, and London is where it lands
Take-up is at record levels. Savills counts 217MW of UK take-up in 2025, up from 212MW in 2024, with 96MW in the fourth quarter alone. CBRE puts London take-up at nearly 193MW in 2025 and projects more than 212MW in 2026, which would be the first year above 200MW. The two sets of figures use different scopes, but they point the same way.
The buyers have changed. CBRE says hyperscalers returned to London in late 2025 after a leasing pause for much of the year, with some leasing campuses of roughly 50MW to 200MW, and that neoclouds are prepared to pay premium rents for core locations and speed to market. CBRE expects demand to outstrip new supply in 2026.
The line is not perfectly straight. JLL reports London colocation vacancy edged up modestly to 7.4% in the second quarter of 2026 as small tranches of new supply reached the market, with 49MW added in the first half. A little new capacity moves the headline rate, which is a sign of how thin the margin is.
The market is concentrated, and the pipeline is thinner than it looks
Concentration is increasing, not easing. Savills puts London at 1,637MW of the UK’s 1,803MW live capacity, or 91%, up from 81% in 2016. Deliveries reached a record 231MW in 2025 after 191MW in 2024, but only 48MW arrived in the first quarter of 2026, and 242MW is under construction across the UK.
Savills is careful about what that pipeline means. Rupert Duckworth of Savills says national supply is expanding on paper, but much of the pipeline remains early-stage and uncertain. The pipeline of the next cycle is also later than it looks. CBRE says campuses planned now, including at Elstree and South Mimms north of London, are expected to enter the market in 2028 or 2029, depending on grid availability.
Regional growth has been slower than the policy ambition. CBRE says the AI Growth Zones have had limited impact so far, with Newcastle, North and South Wales and Culham not yet attracting new data centre investment, although DataVita and QTS have started work on campuses in North Lanarkshire and Cambois. Savills describes the North East as a medium-term diversification story rather than an immediate release valve.
Pre-letting is now the market
Savills says pre-letting has become a core feature of the market, with future capacity increasingly committed well before completion. JLL says partial pre-lets have become the norm across major European markets, with speculative development limited. The practical effect is that capacity visible on a listing is often already spoken for, and the capacity that is genuinely available is usually capacity that has not been built yet.
Power sets the date, and the date sets the project
Power is where the market is tightest. Savills says developers in parts of West London are planning for multi-year waits for firm grid capacity. CBRE calls land with power an increasingly scarce commodity, notes that capacity is constrained in Slough, and says operators are accepting higher latency in exchange for secure, scalable power in areas adjacent to London. JLL says lead times of up to 10 years apply in primary markets.
The queue is the reason. Ofgem’s contracted demand offers reportedly rose from 41GW to 125GW, with at least 80GW attributed to data centres, and Osborne Clarke reports that distribution network operators hold 75GW of grid connection applications, a large proportion of which are speculative. Ofgem is acting to free grid capacity by tackling speculative data centre projects. The government’s response is the Great British Grid, announced at Labour Party Conference on 29 September. GBG is a new publicly owned body within Great British Energy, and the most practical element is the expansion of self-build connection rights. It is a direction of travel rather than a changed date for any project in the queue today.
What a late date costs was shown this month. Reuters reports that Microsoft has pulled out of a deal to anchor Nscale’s Loughton, Essex data centre after grid officials told it they did not expect to supply power until the 2030s. Microsoft said the decision relates to a single site, and Nscale said it remains committed to the project and is exploring alternative power sources. An anchor tenant with a flagship site still left it when the energisation date moved into the next decade.
Capital is plentiful, selective and concentrated
Money is available to projects that look ready. Virtus has closed a £2.45 billion debt facility from 13 banks, including a £1.2 billion green capex facility, behind 18 UK data centres totalling more than 300MW. Osborne Clarke counts £59 billion of investment committed for 52 new UK sites over the next nine years, with 50 of them expected within five.
The same source is clear about the gap between that headline and delivery. Osborne Clarke says many pre-2030 projects in and around London are unlikely to advance before 2030, partly because delivering secured power connections is slowing the release of funding. Kroll says debt is mainly available for de-risked, fully leased assets, which leaves development-stage projects vulnerable.
Equity is more concentrated still. Tracxn data reported by Servnet shows $5.7bn of equity funding across 154 UK data centre infrastructure companies, with only 24 of them having raised any, Nscale accounting for about 65% of the total and London-based companies attracting 93%. A market with this much capital in principle and this little spread across projects is a market where readiness decides who is funded.
Consent is the new gating item
Planning is being rebuilt to move faster. The Register reports that data centres were added to the Nationally Significant Infrastructure Projects regime in 2026, with Wapseys Wood in Buckinghamshire, Ampthill Road in Bedford and New Barn Lane in Dartford admitted, and the reforms intended to cut up to 12 months from approval. The same report says a National Policy Statement setting the criteria is expected in autumn 2026.
Public opposition is moving the other way. The Guardian reported on 22 October that the Sovereign AI Leadership taskforce, which includes Nvidia, Microsoft and Cisco, has told government Britain has roughly 12 months to build a compact that earns public consent. In Norwich, a proposed 150MW data centre with a nearby grid connection has drawn a petition of more than 12,000 signatures, and the South Norfolk Council leader says he will formally object, calling the building too big for the site. In Scotland, approvals for new AI data centres have been paused for up to a year while national guidance is produced.
The signal for developers is that a connection story gets a site to the table but does not carry an application. Noise, water, scale and community benefit are now part of what a project has to show.
What this means in practice
For developers, the sequence that works is power and site control first, then the planning and consent position, then demand at the strongest evidence level available, then capital. A project that has the first and none of the rest is a site, not a pipeline entry.
For operators and offtakers, the market now rewards early commitment. Capacity is pre-let before completion, the new supply that is being planned arrives in 2028 or 2029, and the regions that are growing do so in the medium term. Requirements that are specific about size, density and timing are the ones that can be matched.
For capital, the evidence required has not changed, but consent has been added to it. Funding follows a fixed connection date, signed demand and a credible delivery plan, and the autumn’s news adds a fourth question about whether the local community will let the project proceed.
Related reading
· Data centre grid connection in the UK: timelines, queues and what operators need to know
· Why most UK data centre pipelines fail before they complete
· On-site power generation for data centres in the UK: why the grid queue is accelerating the shift
Sources referenced in this article
· Savills: Spotlight on UK data centres 2026
· CBRE: UK data centre market outlook, midyear review 2026
· JLL: EMEA data centre mid-year 2026 report
· IT Pro: The UK is running on fumes as data centre build-outs can’t keep pace with demand
· Ofgem: Ofgem acts to free grid capacity, tackling speculative data centre projects
· Compare the Cloud: What a 500MW AI data centre means for local suppliers
· GOV.UK: Great British Grid to speed up connections and cut bills
· Reuters via The Star: Microsoft pulls out of UK data center deal with Nscale, Telegraph reports
· Bisnow: UK data centre giant bags £2.45B debt facility
· Kroll: UK data centers, hyperscale growth meets infrastructure fragility
· Servnet: UK data centre investment 2026, Nscale takes nearly two-thirds (citing Tracxn)
· The Register: UK planning reforms to speed up datacenter approvals
· The Guardian via AOL: AI firms say UK has a year to head off datacentre protests
· ITV Anglia: Jake Humphrey joins campaigners against “mega data centre” on the outskirts of Norwich
· Resultsense: Keswick data centre near Norwich, noise and wildlife
· Computing: Scotland delays new AI datacentre approvals for up to a year