Two numbers get conflated constantly in AI infrastructure conversations: the cost of energy, priced in pence per kilowatt-hour, and the cost of deployed compute capacity, priced in pounds per kilowatt per month. They are not the same thing. They do not move together. And comparing one site’s energy rate against another site’s capacity charge produces a number that looks dramatic but means nothing.
This matters because the industry is making multi-decade siting and procurement decisions right now, often on the back of numbers quoted without their unit, their date, or their tier attached. This piece separates energy cost from capacity charge, benchmarks each by generation source and by region using 2026 market data, and sources every figure so it can be checked rather than taken on faith.
Energy costs, by generation source (UK)
Not all power costs the same, even within the same grid, and the assumption that renewables carry a cost premium over conventional generation no longer holds in the UK market. The cleared prices below tell a different story.
| Source | Price (p/kWh) | Basis |
|---|---|---|
| Nuclear SMR (opex target) | 5.5p* | Rolls-Royce target, 2012 prices, not inflation-adjusted to 2026; widely doubted by industry analysts as achievable at commercial scale [1] |
| Solar PV | 6.5p | CfD, cleared Allocation Round 7a auction, February 2026 [2][3] |
| Onshore wind | 7.2p | CfD, cleared Allocation Round 7a auction, February 2026 [2][3] |
| Offshore wind (PPA) | 7.0p | 10-year pay-as-forecast fair value, LevelTen Energy [4] |
| Offshore wind (CfD) | 9.1p | Cleared Allocation Round 7 auction, January 2026 [2][3] |
| Grid wholesale, Q1 2026 | 9.8p | Day-ahead market average [5] |
| Grid wholesale, May-June 2026 | 10.0-11.5p | More current; gas-set price rose on nuclear outages and reduced wind output [6][7][8] |
A genuinely counter-intuitive result sits inside this table: offshore wind’s open-market PPA rate trades below its own government-backed CfD strike price. This is not a data error. A Contract for Difference is a two-way guarantee, the generator is protected when the market price falls, but pays back the difference when it rises above the strike price. That certainty has a cost, and lenders require a higher strike price to make a project bankable even when the underlying merchant PPA rate is trading lower. The two numbers answer different questions: the CfD price is what it costs to make a project financeable, the PPA price is what the electricity is actually changing hands for on the open market.
Read across the table, cleared wind and solar prices, and offshore wind’s PPA rate, currently sit at or below wholesale grid price. Renewables are not the premium procurement route in the UK in 2026, gas-linked wholesale power is now the more expensive default.
Where anaerobic digestion, hydro and biomass sit
These three technologies are deliberately excluded from the table above rather than forced into false comparability with wind and solar. Unlike wind and solar, they do not have a comparable live market price. Most existing UK anaerobic digestion, hydro and biomass capacity was built under legacy Feed-in Tariff, Renewables Obligation, or Renewable Heat Incentive support, schemes now closed to new entrants, so there is no liquid PPA market and no recently-cleared competitive CfD auction price to cite for them [9][10].
What can be said reliably: DESNZ’s own Administrative Strike Prices, the ceiling used to size CfD auction budgets, priced anaerobic digestion (>5MW), hydro (5-50MW) and dedicated biomass with CHP at roughly two to three times the cleared price of wind and solar, in 2024 prices [11][12]. That is a regulatory ceiling and an implied cost-basis estimate, not a transacted market price, and it should be described as such wherever it is referenced externally. The direction of travel is nonetheless a real finding: these technologies carry a structurally higher cost basis than wind and solar in the current UK market, driven by smaller project scale, feedstock cost and, for AD specifically, competition with the biomethane-to-grid market where production costs of EUR 50-120/MWh compete directly against natural gas pricing rather than against grid electricity [13].
Energy costs, by region
Large-user, all-in energy cost varies far more by geography than by generation source, which is the more decision-relevant comparison for site selection.
Europe (large industrial / non-household, p/kWh equivalent):
| Market | Rate | Generation mix note |
|---|---|---|
| Norway | 9p | Hydro-dominant, cheapest in Europe [14] |
| Nordics (Finland, Sweden) | 10-11p | Hydro and nuclear [14][15] |
| UK (wholesale, pre-charges) | 9.8-11.5p | See wholesale note above [5][6][7] |
| France | 15-18p | Nuclear-heavy, historically stable [15][16] |
| UK (large industrial, all-in) | 12-24p | Wide range by contract structure and scale [17] |
| Germany (large industrial) | 10-19p | High policy and grid-fee component even for large users [15][16] |
| Ireland (non-household) | ~23p | Highest in Eurostat’s non-household band, gas-linked [18][19] |
Middle East (industrial, p/kWh equivalent):
| Market | Rate | Note |
|---|---|---|
| Saudi Arabia (industrial) | ~4p | Subsidised; state-backed solar PPAs now clearing near $13/MWh [20][21] |
| UAE (Riyadh/Abu Dhabi industrial) | ~4-5.5p | Subsidised; Abu Dhabi is developing a dedicated cost-reflective tariff specifically for data centres [22][23] |
North America (commercial/industrial, p/kWh equivalent):
| Market | Rate | Note |
|---|---|---|
| Quebec, Canada | ~2.5p | Hydro-dominant, among the world’s cheapest [24] |
| Texas (commercial, deregulated ERCOT) | 4-5.5p | Abundant gas and wind generation, competitive retail market [25][26] |
| US commercial average | ~10.5p | National average, rising with data centre demand [27][28] |
The pattern: a five to eightfold difference in landed energy cost between the Gulf states or Quebec at one end, and Ireland or Germany at the other, inside markets that are all actively competing for the same AI infrastructure investment. Generation mix explains some of this spread, hydro and subsidised gas at the cheap end, gas-linked and policy-heavy markets at the expensive end, but grid constraint and network charges account for at least as much of the gap as the underlying fuel cost.
Deployed capacity cost
This is a distinct number from energy cost: what it costs to reserve power-ready, cooled, secured compute space, billed monthly per kilowatt of committed capacity. It should never be benchmarked directly against a p/kWh energy rate, and it should not be benchmarked against the wrong tier of capacity charge either.
Two pricing tiers exist in this market and are frequently conflated in commentary:
- Standard or wholesale colocation (250kW-4MW, general enterprise workloads): lower per-kW rates, lower rack density, 3-10kW per rack.
- AI/GPU-dense colocation (20-100kW+ per rack, liquid cooling required): meaningfully higher per-kW rates, reflecting the power distribution and cooling premium needed to support modern GPU density [29][30][31].
Major markets, AI/GPU-dense colocation (GBP/kW/month, converted at approximate current FX where sourced in USD):
| Market | Rate | Source basis |
|---|---|---|
| UK, standard racks (5-15kW) | £180-260 | ColoGPU 2026 UK market survey [32] |
| UK, AI/GPU racks (20-50kW) | £230-340 | ColoGPU 2026 UK market survey [32] |
| UK, liquid-cooled (50kW+) | £300-420 | ColoGPU 2026 UK market survey [32] |
| London (Slough/Docklands), wholesale pre-lease | ~£145 | Datacenters.com, Q2 2025 [33] |
| Dallas, US (GPU-aware metro pricing) | £110-190 | QuoteColo metro-level GPU pricing [34] |
| Ashburn/Northern Virginia, US | £145-235 | QuoteColo; CBRE record wholesale >$215/kW [34][35] |
| Chicago, US (wholesale, 250-500kW) | £160-180 | CBRE Global Data Center Trends, Q1 2026 [36] |
| Frankfurt (highest in Europe) | £185-210 | CBRE Global Data Center Trends, Q1 2026 [36] |
| Singapore (highest globally) | £260-375 | CBRE Global Data Center Trends, Q1 2026 [36] |
| Tokyo | £220 | CBRE Global Data Center Trends, Q1 2026 [36] |
| Sydney | £150 | CBRE Global Data Center Trends, Q1 2026 [36] |
| Sao Paulo | £105-150 | CBRE Global Data Center Trends, Q1 2026, most competitive major Latin American market [36] |
Figures vary meaningfully by source depending on whether they reflect asking rents (CBRE’s methodology) or real deal-level quotes (ColoGPU, QuoteColo), and real AI/GPU-dense quotes generally run higher than the general wholesale colocation averages quoted elsewhere in market commentary. A UK capacity charge of £200/kW/month sits within the standard-to-mid AI-rack band domestically, comparable to Frankfurt and to constrained North American markets internationally, and below the UK’s own liquid-cooled, high-density tier. Indicative UK rates by location and format are set out in our data centre cost guide. This is a like-for-like AI/GPU colocation comparison rather than a comparison against general enterprise wholesale colocation, which would understate the true market band and produce a misleadingly favourable comparison.
MENA capacity-charge benchmarks are deliberately not included in this table. The region’s roughly 750MW of installed data centre capacity is overwhelmingly hyperscaler-owned rather than third-party colocation, so a comparable GBP/kW/month colocation market has not yet developed at meaningful scale [37]. The region’s current advantage sits entirely in energy cost, not in capacity pricing, and the two should not be conflated when discussing MENA site economics.
What this means
Energy cost tells you what a megawatt-hour costs to generate and deliver. Capacity charge tells you what a kilowatt of ready, reserved, cooled compute space costs to occupy for a month, for AI-dense deployments specifically, not general enterprise colocation. Conflating the two, or benchmarking one against the wrong tier of the other, produces numbers that look dramatic in a pitch deck but do not hold up under scrutiny. Power commitment, escalation clauses and contract length then change the total, which is explained in the total cost of ownership guide.
The more useful question for operators and offtakers: given your power source, your region, and your deployment density, where do your numbers actually sit against these benchmarks? That comparison, done properly and tier-for-tier, is where the real commercial decisions get made, and where a neutral third party who isn’t selling either side of the deal can add the most value.
Sources
- Centre for Net Zero / Rolls-Royce SMR opex analysis, cited in “How Microgrids Can Solve the UK’s Data Centre Grid Capacity Crisis,” timharper.net, April 2026.
- Contracts for Difference Allocation Round 7 results, GOV.UK / Department for Energy Security and Net Zero, published 14 January 2026, updated 10 February 2026. https://www.gov.uk/government/publications/contracts-for-difference-cfd-allocation-round-7-results
- “Contracts for Difference and the economics of renewable energy deployment,” UK Parliament POST briefing, April 2026. https://post.parliament.uk/contracts-for-difference-and-the-economics-of-renewable-energy-deployment/
- “UK PPA market doubles, with new onshore wind projects in England competitive with CfD,” Veyt / LevelTen Energy, May 2025. https://veyt.com/press-releases/uk-ppa-press-release/
- “UK Wholesale Gas & Electricity Prices 2026: Live Rates,” Connection Technologies, published 17 April 2026, updated 27 April 2026. https://connection-technologies.co.uk/blog/uk-wholesale-gas-electricity-prices-explained-2026
- “Electricity Price Today UK: 25 June 2026,” Selectra. https://selectra.co.uk/energy/guides/tariffs/electricity-prices-today
- “UK Wholesale Energy Prices – 1 June 2026,” TeamEnergy. https://www.teamenergy.com/discover/uk-wholesale-electricity-prices-category/uk-wholesale-energy-prices-1-june-2026/
- Daily UK Energy Market Update, Smart Energy, 3 July 2026. https://www.smart-energy.uk/post/daily-energy-market-report
- “Incentives,” Anaerobic Digestion and Bioresources Association / biogas-info.co.uk. https://www.biogas-info.co.uk/about/incentives/
- “Exploring Farm Anaerobic Digester Economic Viability in a Time of Policy Change in the UK,” MDPI, 2022. https://www.mdpi.com/2227-9717/10/2/212
- CfD Allocation Round 7, second contract budget notice (Administrative Strike Prices, 2024 prices), GOV.UK / DESNZ, December 2025. https://assets.publishing.service.gov.uk/media/6936af01a6fc97b81e57434b/cfd-ar7-second-contract-budget-notice.pdf
- “Contracts for Difference (UK energy),” Wikipedia, referencing DESNZ Allocation Round data, accessed July 2026. https://en.wikipedia.org/wiki/Contracts_for_Difference_(UK_energy)
- “Biomethane Price Trends, Analysis & Forecast,” anaerobic-digestion.com, May 2026. https://blog.anaerobic-digestion.com/biomethane-price-trends-analysis-forecast/
- “Business electricity prices per kWh in Europe — 2026 SME guide,” euenergy, April 2026. https://euenergy.live/articles/business-electricity-prices-per-kwh
- “Prices – Electricity 2026,” IEA. https://www.iea.org/reports/electricity-2026/prices
- “Europe Energy Prices Industry Statistics 2026,” Gitnux, May 2026. https://gitnux.org/europe-energy-prices-industry-statistics/
- Nesta and industry commentary on UK industrial electricity prices, referenced via euenergy 2026 SME guide.
- “Energy in Europe – 2026 edition,” Eurostat. https://ec.europa.eu/eurostat/web/interactive-publications/energy-2026
- “Electricity price statistics,” Eurostat Statistics Explained, May 2026. https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics
- “Monthly Utilities Update – Europe, Middle East & APAC,” Gabelli, November 2025. https://gabelli.com/research/monthly-utilities-update-europe-middle-east-apac/
- Saudi Arabia electricity prices, GlobalPetrolPrices.com, December 2025. https://www.globalpetrolprices.com/Saudi-Arabia/electricity_prices/
- “Abu Dhabi plans dedicated power tariff for AI data centres,” AGBI, January 2026. https://www.agbi.com/energy/2026/01/abu-dhabi-plans-dedicated-power-tariff-for-ai-data-centres/
- “Why Gulf cities are strongly positioned to scale in the AI value chain,” Oxford Economics, February 2026. https://www.oxfordeconomics.com/resource/why-gulf-cities-are-strongly-positioned-to-scale-in-the-ai-value-chain/
- “2026 Colocation Costs & Pricing Overview,” ServerMania, April 2026 (Quebec power cost reference). https://www.servermania.com/kb/articles/server-colocation-cost
- “Texas Business Electricity Rates,” ElectricChoice, June 2026. https://www.electricchoice.com/electricity-prices-by-state/texas/business-electricity/
- “Datacenters and Electricity Costs By the Numbers,” RealClearEnergy, February 2026. https://www.realclearenergy.org/articles/2026/02/12/datacenters_and_electricity_costs_by_the_numbers_1164350.html
- “Electricity Rates by State (July 2026),” Electric Choice. https://www.electricchoice.com/electricity-prices-by-state/
- “Electricity prices to continue rise in 2026,” Utility Dive, citing EIA, November 2025. https://www.utilitydive.com/news/electricity-prices-demand-to-continue-rising-in-2026-eia/805395/
- “Data Center Colocation Pricing: 2026 Cost Per Rack & kW,” Encor Advisors, June 2026. https://encoradvisors.com/data-center-colocation-pricing/
- “AI Data Center Power Requirements 2026: The Grid-to-Chip Guide,” techplustrends.com, April 2026. https://techplustrends.com/ai-data-center-power-requirements-2026-guide/
- “Colocation for AI Workloads: Power, Cooling & GPU Density Requirements Explained,” DataBank, May 2026. https://www.databank.com/resources/blogs/colocation-for-ai-workloads-power-cooling-gpu-density-requirements-explained/
- “Colocation Pricing 2026: What AI Firms Pay,” ColoGPU, April 2026 (UK market survey). https://cologpu.com/blog/colocation-pricing-2026
- “Why Hyperscalers Are Driving Record-High Wholesale Colocation Pricing,” Datacenters.com, August 2025. https://www.datacenters.com/news/hyperscalers-reshape-the-colocation-pricing-landscape
- “AI Infrastructure Cost: What AI Colocation Pricing Really Looks Like in 2026,” QuoteColo, March 2026. https://www.quotecolo.com/blog/colocation-2/ai-colocation-pricing-cost/
- “Single Rack GPU Colocation Pricing & Providers 2026,” QuoteColo, May 2026. https://www.quotecolo.com/single-rack-ai-colocation/
- “Global Data Center Trends 2026,” CBRE, Q1 2026. https://www.cbre.com/insights/reports/global-data-center-trends-2026
- “Monthly Utilities Update – Europe, Middle East & APAC,” Gabelli, November 2025 (MENA installed capacity figure). https://gabelli.com/research/monthly-utilities-update-europe-middle-east-apac/
Methodology note: all figures are indicative benchmarks compiled for a thought-leadership piece from public market reporting, government publications and industry surveys; they are not quotes for a specific deal and should not be relied on as such. USD/EUR to GBP conversions are approximate at rates prevailing in mid-2026 and should be spot-checked against a live rate before external use. Where a figure is a regulatory ceiling or target rather than a transacted market price, this is stated explicitly in the relevant section. Given the pace of change in both energy and colocation markets through 2026, all figures should be re-verified before reuse beyond approximately Q3 2026.