This week in UK data centres:
- Prime Minister Andy Burnham announces Great British Grid at Labour Party Conference on 29 September — a new publicly owned body within Great British Energy designed to invest in electricity network infrastructure and expand self-build connection rights, directly prompted by a data centre pipeline where projects are already proposing to run on gas generators for a decade while waiting for grid access
- AWS secures planning consent for its Iver data centre on 28 September — 30,525 sqm campus replacing 17 existing industrial units, 27 backup generators, with Buckinghamshire Council concluding that the economic and infrastructure benefits outweigh landscape harm — the second significant Iver consent in a market where EIA rigour is now the determining variable
- Bloomberg reports a named UK data centre project is proposing to rely mainly on gas generators for power while waiting at least a decade for a grid connection — the development that appears to have made Great British Grid’s announcement politically unavoidable at the same conference
Great British Grid: announced at Labour Party Conference, prompted by a pipeline proposing gas bridges of a decade or more.
Prime Minister Andy Burnham announced Great British Grid (GBG) at the Labour Party Conference in Liverpool on 29 September 2026. GBG is a new publicly owned body within Great British Energy, tasked with accelerating the delivery of electricity network infrastructure by combining public and private investment. It will work alongside existing network operators rather than replacing them. Initial funding comes from Great British Energy’s existing budgets.
The most significant practical element in the announcement is the expansion of self-build connection rights — giving developers and businesses greater ability to build their own connections where feasible, rather than waiting for network companies. The government cites Ireland, where similar reforms reduced connection times by up to 11 months, as the reference point. GBG will also be able to participate in competitive tendering for transmission projects, potentially introducing new delivery routes for network infrastructure that has previously been the preserve of National Grid and the DNOs.
The announcement’s immediate context was provided by Bloomberg’s reporting on the same day. A planned UK data centre has proposed relying mainly on gas generators for power while it waits at least a decade for a firm grid connection. With demand for connections tripling in less than two years, the proposal illustrates the growing problem of power-network delays that Great British Grid is designed to address. A developer proposing a decade of gas bridge power in a public planning application is the most visible possible demonstration that the current connection system is not functional at the pace the AI infrastructure pipeline requires.
Data Centre Review’s analysis is measured about what GBG will actually deliver for the sector. Great British Grid is not a magic fix for data centre connections. Its most useful role for data centres may lie further upstream — in the transmission and distribution reinforcement that creates the network headroom developers need — rather than in accelerating the final connection into individual sites. Until the operational scope of GBG is confirmed, the practical benefit to the data centre pipeline is genuinely difficult to quantify. What is clear is that the political pressure to act has now produced a formal government response.
For developers and operators who have been managing the grid constraint as a structural feature of the UK market, GBG is an important signal of direction rather than an immediate operational change. Self-build connection rights, if implemented at the scale the announcement implies, could materially change the timeline for projects with the capital and technical capability to build their own connection infrastructure. That is a smaller subset of the pipeline than the headline suggests — but for the right projects, it is meaningful.
Sources: Great British Grid to speed up connections and cut bills — GOV.UK | Can Great British Grid actually speed up data centre connections? — Data Centre Review | UK Data Center Turns to Gas as Burnham Moves to Fix Grid Delays — Bloomberg | Great British Grid aims to speed up connections for UK businesses — The Manufacturer | Plans for Great British Grid to speed up connections — Government Business
AWS wins Iver consent. The EIA rigour is now the planning variable that matters.
Buckinghamshire Council granted planning permission on 28 September for AWS’s data centre at the Ridgeway Distribution Centre in Iver. The campus covers 30,525 sqm, replaces 17 existing industrial and warehouse units, and includes a single two-storey data centre building, MV building, substation compound with two switchrooms, and a generator yard with 27 backup generators. AWS will invest £73,000 in improving public rights of way near the site as part of the consent.
Planning officers acknowledged that the development would cause some harm to the surrounding landscape and the Colne Valley Regional Park. They concluded that the need for data centres, employment benefits, and an expected reduction in vehicle movements outweighed that harm. The Iver location — a few miles east of Slough, the largest data centre hub in greater London — places the development in proximity to established connectivity and power infrastructure.
The Iver consent sits in a specific planning context. Foxglove’s judicial review of a separate Iver hyperscale application — which produced the government’s January 2026 concession that granting permission without a full EIA was a serious logical error — established that environmental mitigation commitments must be binding and enforceable. AWS’s application, with its detailed EIA supporting the development, binding mitigation commitments, and measurable infrastructure benefits, represents the post-Foxglove standard being applied in practice. Landscape harm acknowledged, quantified, and outweighed by documented public benefits — not aspirational environmental statements.
For operators and developers tracking the London and South East pipeline, the Iver consent reinforces what has been visible since the Foxglove concession: applications with rigorous EIA support, binding mitigation conditions, and a clear public benefit case are getting through. Applications relying on aspirational language are not.
Sources: AWS granted planning permission for data center in Iver, UK — Data Centre Dynamics | AWS wins approval for Iver data centre despite environmental concerns — Techerati | Huge 7.3-hectare Amazon data centre approved in Buckinghamshire — Bucks Herald
The week in one line: the government announced Great British Grid at Labour Party Conference — a public investment vehicle for grid infrastructure with self-build connection rights at its core — on the same day Bloomberg reported a UK data centre project proposing to run on gas for a decade waiting for grid access, making the political necessity of the announcement plain; and AWS won Iver consent on binding EIA conditions, the latest illustration of what post-Foxglove planning looks like in practice.
Armason tracks infrastructure signals across the UK and European data centre market. For site availability, grid intelligence, or pipeline advisory, visit armason.co.uk.
Related reading
· UK Data Centre Intelligence — Week Commencing 21 September 2026
· Data centre grid connection in the UK: timelines, queues and what operators need to know
· Why most UK data centre pipelines fail before they complete


