The Ofgem Data Centre Commitment Fee: what operators with grid positions need to do before 16 September

High voltage power lines at dusk

Ofgem’s consultation on the Data Centre Commitment Fee closes on 16 September 2026. The proposals, published under the CURATE programme alongside the wider TMO4+ gated connections reform, would require data centre developers to pay a fee of between £237,500 and £712,500 per MW when accepting a grid connection offer — refundable on energisation, forfeited on exit. For a 40MW project, the commitment ranges from £9.5m to £28.5m.

The consultation is generating serious legal and commercial scrutiny. Slaughter and May have characterised the proposals as a potential cull rather than a curation — a mechanism that will remove a significant proportion of current queue positions through a combination of financial commitment and mandatory progress milestones. For operators with genuine projects in the queue, this article explains what the fee means in practice and what needs to happen before the consultation closes.

Why Ofgem is doing this

The grid connection queue for data centres has grown to a size that makes rational planning impossible. Contracted demand connection applications rose from 41GW in November 2024 to 125GW by June 2025, with data centres accounting for at least 73GW of that total. The queue contains 315 data centre projects requesting around 73GW of capacity — substantially more than Britain’s peak electricity demand of approximately 45GW.

The vast majority of these applications are not going to be built. Some are speculative positions held by developers who want optionality without commitment. Some are held by projects that have no realistic prospect of securing planning consent, capital, or customers at the scale their connection application implies. Some are contingency applications by projects that have already secured a connection elsewhere.

The consequence for projects that are genuinely deliverable is a queue that they cannot move through, a National Grid that cannot plan investment with confidence, and connection timelines that are extending into the 2030s in some areas. Ofgem’s stated position is explicit: not all 315 projects will connect, and the commitment fee is designed to force projects to declare whether they are serious before the queue consumes further capacity.

How the fee works in practice

The fee structure

The proposed fee is set at between 2.5% and 7.5% of assumed average data centre capex per MW, with average capex assumed at £9.5m per MW. Herbert Smith Freehills Kramer have noted that the fee functions as a performance bond rather than a cost — for a committed project that proceeds to energisation, the financial exposure is the opportunity cost of the locked capital during the construction period, not the fee amount itself.

The fee is paid when accepting a connection offer. It is refunded in full on energisation of the connection. It is forfeited if the project exits the queue after accepting a connection offer. For projects that are currently holding a queue position but have not yet received a connection offer, the fee will apply at the point an offer is accepted — which may be years away depending on where the project sits in the reformed queue.

The milestone requirements

The milestone requirements that accompany the fee are drawing more attention than the financial figure in legal analysis. Addleshaw Goddard note that projects must satisfy readiness and strategic alignment criteria at defined intervals to retain their queue position. The proposed milestones include: demonstrating financial capability, evidencing commercial maturity (which includes demonstrating committed end-user demand), and showing procurement activity at defined stages.

The end-user demand requirement is the most significant for speculative projects. If adopted, the requirement to demonstrate committed demand before securing capacity would fundamentally change the speculative development model — a project without a contracted offtaker would not be able to hold a queue position regardless of its financial capability.

For projects that do have committed demand, this requirement is beneficial: it clears queue positions held by projects that are competing for the same grid capacity without any intention to serve an actual customer.

What operators with genuine projects need to assess

Is the queue position worth holding?

The first question for any operator with a current queue position is whether the position is worth holding under the reformed framework. A project that entered the queue at one voltage level or capacity with a different business case from what it holds today needs to assess whether the connection offer, when it arrives, will match the project’s actual requirements.

Projects that are holding positions as optionality — without a confirmed site, confirmed planning route, or confirmed capital — should use the consultation period to assess whether the commitment fee and milestone requirements change the calculus of holding those positions.

Can the milestones be met?

For projects intending to proceed, the milestone assessment is practical. Does the project have financial capability that can be evidenced to Ofgem’s satisfaction? Does it have a planning application filed or a planning route confirmed? Does it have contracted end-user demand, or a credible pipeline of demand that can be evidenced at the required stage?

Projects that cannot meet the milestone requirements at the relevant stages will lose their queue position. The milestone schedule is not a formality — it is the mechanism by which the queue is cleared of projects that cannot demonstrate progress.

Should the consultation response be submitted?

Operators with material queue positions should consider whether to submit to the consultation. The consultation is open to anyone with an interest in the outcome. Operators whose projects would be adversely affected by specific elements of the proposal — the fee level, the milestone schedule, the definition of committed end-user demand — have the opportunity to make that case directly to Ofgem before the framework is finalised.

The consultation closes 16 September 2026. Responses submitted after that date will not be considered in the final determination.

The broader significance for UK data centre development

The CURATE consultation sits alongside the TMO4+ reforms already in effect, which introduced the first-ready-first-connected principle and gated connection milestones for all connection applicants. Together, these reforms represent the most significant restructuring of the UK grid connection regime for data centres in the sector’s history. JD Supra note that the combination of the fee and the milestone requirements is designed to ensure that only projects with genuine delivery capability hold queue positions — and that the reformed queue will be materially shorter and more predictable than the current one.

For developers with genuine projects who have been competing against speculative queue positions for grid capacity, that outcome is beneficial. The reformed queue will be shorter, the connection offers that emerge from it will be more credible, and the timeline from application to energisation will compress as speculative positions are cleared.

For the wider development market, the commitment fee and demand milestone requirements add a new dimension to the development decision. A project that cannot demonstrate committed demand before accepting a connection offer is carrying a commitment it cannot convert — and will forfeit the fee if it exits. The discipline this imposes on development sequencing is exactly what the market needs: power confirmed before capital is committed, demand secured before connections are accepted.

Armason: grid intelligence and sequencing advisory for UK data centre developers

Armason tracks grid connection status, queue positions, and development sequencing across the UK market. We work with operators and developers on the dependency chain — power, demand, capital, planning — that determines whether a development programme can meet the milestone requirements the reformed regime demands.

If you are evaluating the impact of the CURATE proposals on a current queue position or development programme, contact the Armason team.

Related reading

· Ofgem first ready first connected: what the grid queue reform means for data centre developers

· Data centre grid connection in the UK: timelines, queues and what operators need to know

· Why most UK data centre pipelines fail before they complete

· On-site power generation for UK data centres: when gas, solar, and battery storage make commercial sense

Sources referenced in this article

· Ofgem acts to free up grid capacity by tackling speculative data centre projects — Ofgem

· Pay to Stay: Ofgem’s plan to cull the data centre connection queue — Slaughter and May

· Ofgem’s CURATE consultation: what it means for grid connected data centre projects — Addleshaw Goddard

· UK Grid Connections Reform: Ofgem’s Data Centre Fee Proposals — Herbert Smith Freehills Kramer

· UK Grid Connections Reform: Ofgem Proposals for New Data Centre Commitment Fee — JD Supra

· TMO4+ Impact Assessment — Ofgem

· UK energy regulator promises power crackdown for data centres — Capacity Global

Related Insights
Work With Armason

If you’re sourcing data centre capacity or delivering it, we can help structure the engagement.

MI Roundup

Weekly market intelligence, every Monday.