Relocating a data center: the move is the cheap part, finding capacity by your date is not
Armason · Market Intelligence · November 2026 · armason.co.uk
Most guides to relocating a data center are about the move. Pack, ship, rack, test. Info-Tech’s widely quoted survey puts it at about $10,000 a rack, and that is the number everyone repeats. What we see across the capacity we track from operators is different: the move is rarely what decides whether a relocation works. What decides it is whether capacity of your size, density and date exists at all. Armason introduces buyers to operators in the US, Europe and the UK, so this is a view from the supply side of the table.
Moving costs below are published benchmarks, attributed and in the currency they were published in. Availability and asking rates are what operators have given us for our capacity map in November 2026. Asking rates are per kW of contracted IT load per month with power on top, and they are asks, not signed prices. We do not name operators.
What the market presents, and what we see
The market presents plenty of capacity. Every operator has a pipeline, and announcements run years ahead. What we see when we ask for dates is narrower. What can be contracted now is mostly in blocks of a few MW per site, such as 0.5 to 5MW across UK sites and about 6MW in Dublin. The larger blocks, 20MW to 100MW and beyond, are 2027 and 2028 deliveries.
That changes what a relocation is. If you need 1MW in the UK, you are choosing between several sites. If you need 10MW or more, you may be choosing between a handful of dates, and the early ones go to whoever commits first.
Start with the date, not the rent
A relocation has a hard deadline: the lease on the old site. A colocation-to-colocation move with no hardware change takes 6 to 12 weeks, a legacy site to high density 8 to 16 weeks, and longer with liquid cooling. The search and contract can take 2 to 6 weeks of that. Add the time an operator needs to deliver, and the plan has to start well before the old contract ends. Where the capacity you want is a 2027 delivery, the old lease is the part you have to manage, so ask early about a short extension rather than at the end.
What the move itself costs
For the move alone, the average relocation costs about $120,000, or $10,000 a rack. Metro Colo Advisory estimates under 10 racks at $50,000 to $150,000, 10 to 50 racks at $200,000 to $750,000, and large estates from $1 million, and Optrium puts a UK average at around £120,000, about £10,000 a rack. These cover planning, movers, transport, insurance, installation and testing. They exclude the new rent and any new hardware. Use them as a check, not a forecast: dense or liquid-cooled equipment costs more to move than a standard rack.
What sits around the move
You will usually pay for two sites at once while old and new run in parallel, so budget for the overlap. Add one-time fees for the cage, power and access, and circuits between the sites. Cross-connect pricing varies by region: Inflect cites one-time installs of $100 to $500 and monthly fees of $150 to $300, while TeleGeography found the median fiber cross-connect at $300 in North America against $58 in Europe. Network is often the hardest part to sequence, because carrier and IP changes have to land around the cutover. The old contract has its own costs: notice, renewal, early exit, restoration and decommissioning.
The rent decides whether it was worth it
The move is a one-off, and the rent runs for the whole new term. On our map, asking rates are wide. UK asks run from about £90 to £195 per kW per month, with London-area sites at £135 to £195. Europe sits at roughly €130 to €200, and the US at $150 to $235. As illustrative arithmetic, not a quote: 20 racks at 10kW is 200kW, and a site asking £20 per kW less saves £4,000 a month. At about £10,000 a rack, the same move costs about £200,000, so rent alone takes around four years to repay it.
So most moves are not made to save rent. They are made because the lease is ending, the site cannot supply more power, or the workload needs more density than the building can give. When that is the driver, the job is to find capacity that meets the date and the density, then bring the cost down with what the new provider will cover.
What a new provider may cover
A provider competing for the deployment may offer free or reduced months at the start, waived setup fees, waived cross-connect installation, migration credits or remote hands hours. These are negotiable and not guaranteed, and a provider will not normally cover downtime, hardware refresh or the whole move. Ask before you sign.
Relocating in London
On our capacity map, London-area asking rates for smaller footprints run from £135 to £195 per kW per month, and the sites we hold there are blocks of a few MW each, with more arriving in 2027. That suits a footprint of a few hundred kW to a few MW. A larger move often has more choice outside the M25, where the lowest UK asks we hold are well below the London range, down to about £90. See our colocation pricing guide for the full spread.
Moving for density
Many moves now start with density, not rent. A building designed for 5 to 10kW a rack cannot take 40kW racks without major work. If the destination has to provide liquid cooling, allow more time and test the cooling design before you commit.
How to compare moving with staying
Put both on one basis over the new term. Staying is the renewal rent plus any upgrade. Moving is the relocation project, the overlap, setup, circuits, old-contract exit and new rent. Then ask what a provider will cover. Our cost of compute calculator and GPU cluster planner help set larger deployments out like for like.
Armason: neutral introductions between sites, demand and capital
Armason introduces businesses that need capacity to operators who can deliver it, in the US, Europe, the UK and beyond, with no bias towards either side of a transaction. If you are planning a move and want to know what is available at your size, density and date, we would like to hear from you.
This article is general information. Moving costs are published benchmarks from the sources listed and vary by project. Armason figures are asking rates from operators as at November 2026 and are not contract prices. It is not investment or legal advice.
Related reading
· Data centre offtake UK: how demand gets matched to capacity in a constrained market
Sources referenced in this article
· Info-Tech Research Group: Data center relocation budget tool
· Metro Colo Advisory: Data center migration and relocation, cost, checklist and plan
· Optrium: How much does it cost to migrate a data centre?
· Inflect: Colocation pricing, what to expect in 2026
· Fierce Network: Study, US fiber cross-connect pricing higher than Europe (TeleGeography)