Insights/Article

Behind the meter at UK data centres: when private wire and on-site generation make commercial sense

Cooling tower of a power plant

Behind-the-meter power — generation that connects directly to the consumer without routing through the public grid — has moved from contingency planning to primary development strategy for a significant and growing proportion of the UK data centre market. The shift is structural: grid connection timelines in high-demand areas now extend well beyond the capital requirements of most development programmes, and the cost of waiting has become greater than the cost of generating independently.

Linklaters’ Powered Land series documented the transition explicitly: private wire networks and co-located power generation have moved from interim measures to structural development strategy, as developers decouple from the congested national grid. Kao Data’s 40MW private wire solar deal at Harlow, completed in March 2026, is the most concrete public example of a credible UK colocation operator treating private wire as a primary power model. It will not be the last.

This article covers the commercial logic of behind-the-meter power for UK data centres, how deals are being structured, the site characteristics that make it viable, and the regulatory and legal framework that applies.

The commercial logic

Avoiding grid charges

The most immediate commercial advantage of behind-the-meter power is the avoidance of grid charges. A consumer taking power from the public grid pays the energy cost plus network charges — Transmission Network Use of System (TNUoS), Distribution Use of System (DUoS), the Balancing Services Use of System charge (BSUoS), and policy levies including Renewable Obligation costs and Contracts for Difference. These charges can add 30 to 50% to the wholesale energy cost, depending on the voltage level and the time of consumption.

A private wire consumer who takes power directly from a co-located generation asset avoids most of these charges on the power flowing through the private wire. The saving is material at data centre scale. For a 40MW campus operating at 80% average utilisation, the avoided grid charges across a 15-year PPA term represent a significant capital-equivalent saving.

Grid independence

Grid independence — the ability to operate without relying on a public grid connection — is becoming commercially significant for a specific class of AI workloads. AI training requirements of 100MW and above are not latency-sensitive and follow available power rather than proximity to demand centres. A campus that is energised from co-located generation can be located where power is available, rather than where the grid connection queue is shortest.

This is the characteristic that makes behind-the-meter power viable at hyperscale: the workload can move to the power rather than requiring the power to come to the workload. It opens site locations in Scotland, Wales, the English regions, and elsewhere that would not be viable on a grid-connection-first basis.

Sustainability credentials

For operators whose enterprise and hyperscaler customers have Scope 2 emissions reporting requirements, directly consumed renewable power — power that flows from a renewable generation asset through a private wire to the data centre — carries stronger sustainability credentials than grid power backed by REGOs. The distinction matters in the current market, where hyperscaler procurement criteria for colocation capacity increasingly specify 100% renewable power with direct consumption evidence rather than certificate-backed claims.

How deals are being structured

The Kao Data / Downing model

The Kao Data / Downing Renewable Developments deal at Harlow is the reference point for UK private wire at scale. Downing’s Green Data Solar Farm connects directly to the Kao Data campus via a dedicated private wire route, delivering up to 40MW of solar power without routing through the public network. The arrangement addresses energy availability, power pricing, and grid delay simultaneously — the three challenges Kao Data identified as leading constraints on UK data centre operators.

The commercial structure is a long-term offtake agreement between the generation developer and the data centre operator, with the private wire infrastructure owned or maintained under a shared arrangement. The deal also delivers verified renewable power supporting Kao Data’s carbon reduction commitments, without REGO certificates — direct consumption evidence.

The DataVita / NWF model

The DataVita Lanarkshire campus demonstrates a different structure: a major data centre development backed by a National Wealth Fund guarantee, with CoreWeave contracted as the anchor tenant on a 15-year lease, targeting 500MW of on-site power generation at full buildout. The power model at DataVita combines grid connection — Lanarkshire has access to industrial-heritage grid infrastructure — with a longer-term on-site generation strategy. The NWF guarantee converted Armason’s Capital Unlock thesis into practice: committed offtaker demand made the financing possible, and the on-site generation target provides the power independence the campus will need as it scales beyond what grid capacity alone can support.

Site characteristics that make behind-the-meter viable

Adjacent generation potential

The most important site characteristic for private wire viability is proximity to a generation asset or to land suitable for developing one. A solar farm requires open land with suitable grid export rights (or the generation is solely for direct consumption). A wind turbine requires planning consent and sufficient wind resource. A gas turbine can be sited more flexibly but requires fuel supply infrastructure and an environmental permit.

The economics of private wire improve as the cable distance between generation and consumption decreases. A generation asset on the same site or immediately adjacent — sharing the site boundary — requires minimal cable infrastructure and wayleave negotiation. A generation asset 5km away requires a cable route across potentially multiple land parcels, with wayleave agreements for each, adding cost and legal complexity.

Industrial heritage and existing power infrastructure

Former industrial sites — power stations, steelworks, chemical plants — often carry existing high-voltage power infrastructure, substation assets, and grid connections that can be repurposed for data centre use. The Cottam power station proposal in Nottinghamshire and the former steelwork sites being evaluated in South Wales both represent this category. More than 125GW of energy and data centre projects are currently waiting for National Grid access — the sites that already have power infrastructure are at a structural advantage.

Load profile compatibility

Solar generation produces power during daylight hours with a profile that peaks at midday. A data centre running AI training workloads at constant high utilisation has a flat load profile that does not naturally match solar generation. Private wire from a solar farm makes most commercial sense when the data centre operator can shift workloads — scheduling high-intensity AI training during peak solar generation hours — or when the arrangement is supplemented by battery storage or a grid connection that provides power outside solar generation hours.

The regulatory and legal framework

Ofgem and the grid code

A private wire arrangement that connects a generation asset directly to a consumer without passing through the public network is exempt from most grid code requirements — it is not a licensed electricity distribution activity. However, where the data centre also holds a grid connection as a backup or supplementary supply, the interaction between the private wire and the grid connection requires careful structuring to comply with the Distribution Connection and Use of System Agreement and the relevant DNO’s technical standards.

Wayleave agreements

Where the private wire route crosses third-party land, wayleave agreements are required for each land parcel. Statutory wayleave rights under the Electricity Act 1989 provide a route to secure access where agreement cannot be reached, but the process is time-consuming. Developers who identify the cable route and begin wayleave negotiations early — before the development programme is committed — reduce the risk of the connection being delayed by a wayleave dispute.

Environmental permits

On-site generation assets — gas turbines, diesel generators, fuel cells — require environmental permits from the Environment Agency covering noise, air quality, and emissions. The conditions of those permits determine the operational constraints on the generation asset: hours of operation, fuel type, emissions limits. DataVita’s specification of HVO generators under a SEPA permit at DV4 is an example of how environmental permit compliance is being addressed in the current planning environment. Applications that propose diesel generation without addressing the environmental permit position are vulnerable to planning conditions that constrain operational hours.

What Great British Grid means for behind-the-meter power

The government’s announcement of Great British Grid on 29 September 2026 includes expanded self-build connection rights — a mechanism that gives developers and businesses greater ability to build their own connections where feasible. This is an extension of behind-the-meter logic into the connection infrastructure itself: rather than waiting for a DNO to build a connection, the developer builds it. The practical benefit depends on the scope of the self-build rights and the regulatory framework for self-built connections, which is still being defined.

For developers evaluating behind-the-meter power strategies, Great British Grid does not change the immediate commercial logic of private wire or on-site generation — those decisions are driven by current grid connection timelines and the capital requirements of the development programme. What GBG signals is that the government has recognised private and self-built power infrastructure as part of the solution to the grid constraint, rather than a workaround to be tolerated. That changes the regulatory risk profile of behind-the-meter strategies for the medium term.

Related reading

· Data centre power strategy UK: grid connection, private wire, PPA, and on-site generation in 2026

· Data centre site selection in the UK: the new sequence in a power-first market

· Ofgem first ready first connected: what the grid queue reform means for data centre developers

· On-site power generation for UK data centres: when gas, solar, and battery storage make commercial sense

Sources referenced in this article

· Powered Land Part 3: co-locating power and data centres — Linklaters

· Pioneering project to supply Kao Data with up to 40MW of solar electricity — Intelligent Data Centres

· Solar for data centres: powering UK data centre growth — Evo Energy

· DataVita secures £300m for data centre rollout — National Wealth Fund

· Mastering powered land transactions for UK data centres — BCLP

· Futureproofing data centres: grid constraints and alternative power strategies — SHMA

· Great British Grid to speed up connections and cut bills — GOV.UK

· DataVita submits £850m DV4 plans in Scotland’s first AI Growth Zone — Data Centre Review

· EMEA data centre mid-year 2026 report — JLL

Related Insights
Work With Armason

If you’re sourcing data centre capacity or delivering it, we can help structure the engagement.

MI Roundup

Weekly market intelligence, every Monday.