Insights/Article

Ofgem first ready first connected: what the grid queue reform means for data centre developers

High-voltage electrical substation

The UK grid connection queue has been one of the most significant barriers to data centre development for the past three years. A system that worked adequately when application volumes were modest has been overwhelmed by unprecedented demand, resulting in connection timelines that stretch to a decade and a queue filled with speculative projects that have no realistic prospect of completion.

That system is now being fundamentally reformed. Ofgem’s TMO4+ reforms — the first ready and needed, first connected framework — represent the most significant change to UK grid connection process in a generation. For data centre developers and investors, understanding what the reform means in practice is now a matter of commercial urgency.

What the reform is and why it happened

The grid connection queue grew from 41GW of demand in November 2024 to 125GW by June 2025 — a tripling in just seven months. Roughly 50GW of that total was linked to data centre developments, many at early or speculative stages. The scale and pace of growth exposed structural weaknesses in the way demand projects secured grid access.

The previous system operated on a first-come, first-served basis. A project could join the queue by submitting an application with minimal evidence of readiness or financial commitment. The result was a queue dominated by projects that had no land rights, no planning consent, and no realistic development timeline — the so-called zombie projects that were blocking viable schemes behind them.

On 15 April 2025, Ofgem approved the TMO4+ package of reforms, replacing the first-come, first-served model with a first ready and needed, first connected process. The reform requires all projects seeking grid connection to demonstrate that they are genuinely able to progress before they can secure a place in the reformed queue.

The TMO4+ reforms represent the most significant change to the UK grid connection process in a generation. Being early in the queue no longer confers an advantage. Being ready does.

What first ready first connected means in practice

The Gate 2 process

Under the reformed framework, projects must pass through a Gate 2 assessment to secure a confirmed place in the connection queue. Gate 2 requires projects to demonstrate two things: strategic alignment and readiness.

Strategic alignment means the project must be consistent with the government’s long-term energy plans, including the Clean Power 2030 Action Plan and, in due course, the Strategic Spatial Energy Plan. In practice, projects located in or aligned with AI Growth Zones, or those that can demonstrate clear strategic benefit to the electricity system, will be better positioned under this criterion.

Readiness criteria require projects to demonstrate that they hold exclusive land rights — an option, lease, or ownership — over the site. For projects pursuing the Development Consent Order route, applicants must have submitted and validated a planning application. The intent is to ensure that only projects with a genuine and near-term prospect of delivery can hold a position in the queue.

What happens to projects already in the queue

Projects already in the existing queue were given a grace period to demonstrate they meet the Gate 2 criteria. Those that do can retain their existing connection date or request an accelerated connection date based on the reduced queue. Projects that do not meet the Gate 2 criteria revert to an indicative connection date and lose their confirmed position in the queue.

Certain projects receive protected status — those scheduled for commissioning in 2026, and those that hold a Contract for Difference, a Capacity Market agreement, or full planning permission. These projects retain their existing offers regardless of Gate 2 outcome.

The data centre specific complication

Ofgem’s own decision acknowledges that the timing of data centres acquiring land rights — typically later in their development process than other types of connectees — means they may be particularly disadvantaged by the readiness requirements. A data centre developer who has been working through feasibility and design without yet securing land rights may find that projects that started the planning process earlier — with land already controlled — are prioritised ahead of them regardless of their relative commercial readiness.

This creates a specific strategic implication for data centre developers: securing land rights early — not just optioning land — is now a gate-keeping step for queue access, not merely a development milestone.

For data centre developers, securing land rights is now a prerequisite for queue access under the reformed framework. Projects that have not yet formalised land control face a structural disadvantage relative to those that have.

The Connect Accelerate and Connect Operate workstreams

The TMO4+ reforms are the foundation of a broader programme of grid connection reform that Ofgem is continuing to develop through 2026 and beyond. Two workstreams are particularly relevant for data centre developers.

Connect Accelerate

Connect Accelerate is exploring reform to allow greater self-build and ownership of high-voltage assets, including the self-build and transfer of infrastructure to network operators on completion. This would allow data centre developers to take more direct control of the infrastructure required for their connection, potentially compressing timelines significantly for projects with the capital and capability to build their own grid assets.

An Independent Transmission Owner licence is also under consideration, which would allow more flexible and hybrid grid configurations. For large-scale data centre campuses requiring bespoke grid arrangements, this could open materially new options for how connections are structured and financed.

Connect Operate

Connect Operate is examining how large demand customers interact with the grid once connected. Ofgem is considering contracting arrangements that could increase the capacity available for demand connection, requirements to minimise the negative impact of large demand on the grid, and mechanisms that could allow data centres to contribute positively to grid operation.

The practical implication of Connect Operate for data centre operators is significant. Ofgem is actively considering mandatory curtailment during periods of grid stress, and flexibility arrangements — where operators reduce consumption or shift load in exchange for earlier connection or lower charges — as tools to manage the system. Data centres that can demonstrate demand flexibility may access the grid faster than those that cannot.

Demand flexibility is becoming a route to faster grid access, not just a sustainability commitment. Operators who design flexibility into their facilities from day one may secure connection timelines that would otherwise be unavailable.

The Connection Acceleration Service

Alongside the regulatory reforms, the government has established the Connection Acceleration Service (CAS) — a coordinated programme bringing together DESNZ, the Office for Investment, network companies, Ofgem, and NESO to support strategically important projects facing grid connection delays. The pilot phase launched in December 2025 and supports projects including data centres, gigafactories, and hospitals.

The CAS builds on an informal triage service that the government has operated for several years. That service has secured or safeguarded over £35 billion of investment across data centres and other strategic sectors by helping developers navigate the connection process more effectively.

For data centre developers with projects that are genuinely strategically significant — large-scale AI infrastructure, projects in AI Growth Zones, or developments with committed hyperscale demand — engaging with the CAS may provide access to connection pathways that are not available through the standard queue.

What this means for site selection and development strategy

The reform programme changes data centre development strategy in several important ways.

Land rights first. Under the reformed framework, securing land rights is not just a development milestone — it is a gate-keeping requirement for queue access. Developers who option land but delay formal control risk being unable to demonstrate readiness when the Gate 2 window opens.

Planning position matters more than ever. Projects with outline or full planning consent are better positioned for both Gate 2 readiness criteria and for protected status. Investing in planning earlier in the development process — rather than treating it as a post-connection step — is now strategically important.

AI Growth Zone alignment creates a queue advantage. Projects located in or aligned with AI Growth Zones may receive preferential treatment for connection under the strategic alignment criteria. For developers evaluating site selection, AI Growth Zone proximity is now a grid access variable as well as a planning one.

Flexibility should be designed in from the outset. As Connect Operate develops, demand flexibility is likely to become an increasingly important lever for accessing grid capacity. Data centres designed for flexible operation from the outset — with the ability to shift or reduce load during grid stress events — will be better positioned to take advantage of flexibility-linked connection options.

The developers who will define the next phase of UK data centre development are those who treat grid access as a primary design constraint, not a post-site-selection problem to be solved.

Armason: grid intelligence and execution-ready sites

Armason tracks grid connection status, queue position, and regulatory developments across the UK data centre and AI infrastructure market. We advise developers and investors on how to navigate the reformed connection process, identify sites where grid access has already been secured, and structure development programmes that are positioned for success under the new framework.

We have sites available now with land secured and grid connections in place — positions that pre-date the queue reform and are not subject to the Gate 2 assessment process. For developers who need to move now rather than wait for the reformed queue to deliver, these represent a meaningful alternative to the standard market.

If the grid connection reform is affecting your development timeline or investment strategy, we would like to talk.

Contact the Armason team to discuss grid connectivity, site availability, and regulatory advisory.

Related reading

Data centre grid connection in the UK: timelines, queues and what operators need to know

Finding data centre sites with power in the UK: why grid connectivity is now the critical constraint

Data centre investment in the UK: why capital is abundant and execution is not

Sources referenced in this article

Ofgem approves Great Britain’s grid connections reform — Latham and Watkins

UK grid connections reform: impact on data centres — Norton Rose Fulbright

Ofgem launches sweeping review of grid connections as data centre demand surges — Computing

Connect update: demand connections reform — Ofgem

Accelerating electricity network connections for strategic demand — GOV.UK

Data centre grid connections could be reshaped by Ofgem — Techerati

First ready first connected: reform to GB electricity grid connections — Norton Rose Fulbright

Related Insights
Work With Armason

If you’re sourcing data centre capacity or delivering it, we can help structure the engagement.

MI Roundup

Weekly market intelligence, every Monday.