UK Data Centre Intelligence — Week Commencing 29 June 2026
This week in UK data centres:
A £12bn data centre campus proposed for North Devon farmland — and hundreds of locals gathered in a town hall to oppose it
Savills published its H1 2026 UK data centre report: execution is now the decisive variable
Ofgem’s grid reform continues to reshape the competitive dynamics of data centre development
A 1.5GW data centre proposed for North Devon. The planning battle has begun.
Xlinks has proposed a large AI data and energy storage development at Alverdiscott, Devon. The campus comprises two separate planning proposals submitted to Torridge District Council: a 1.5GW large-scale AI data centre campus known as Valeon, and a 1.8GW on-site battery energy storage facility to support it. The project would total more than £12 billion in investment.
The site between Great Torrington, Huntshaw and Weare Gifford has been chosen because of its mild, year-round temperatures and plentiful access to clean power from nearby solar and wind, with spare capacity at the Alverdiscott substation. The private wire approach — connecting the data centre to the battery storage through underground cables — is designed to ensure consistent power if the grid is temporarily disrupted. It is a model that sidesteps the grid queue entirely.
Campaigners against the plans filled Torrington Town Hall at a public meeting on June 29, with hundreds more gathered on the street outside. Local opposition described the proposals as causing utter horror, with concerns focusing on noise, water use, landscape impact, and the scale of industrial development on agricultural land in a rural setting.
The Devon project illustrates two things simultaneously: that developers are now looking well beyond the M25 to find sites with available power, and that the planning battles that come with that geographic shift are real and likely to intensify.
No planning application has yet been submitted. Torridge District Council confirmed on 30 June 2026 that it had not received any application. Public consultation runs from July 14 to August 11.
Source: Data Centre Dynamics — 1.5GW data center campus proposed in Devon, UK | Farmers Guardian — Farmers oppose huge data centre in North Devon countryside
Savills H1 2026: execution is the decisive variable.
Savills published its H1 2026 UK data centre building capacity spotlight this week, with a clear editorial line: the UK is unlikely to lack demand, capital or strategic relevance. The decisive question is which projects can convert those advantages into deliverable capacity in a more constrained, regulated and execution-sensitive environment.
The report’s key findings map closely to what the market has been signalling for several months. Power is the primary gatekeeper of growth — grid reform should improve queue discipline but will not eliminate the underlying capacity scarcity. Land strategy is no longer just about the site itself but about securing the wider corridor of rights needed for development: third-party consents for cable routes, pipework and access are increasingly on the critical path. Construction has become a major execution filter — rising costs, specialist labour shortages, and long lead times for key equipment are widening the gap between consented projects and operational stock.
Supply and demand remain exceptionally tight. New deliveries are being rapidly absorbed, leaving the market increasingly reliant on pre-commitment, while the vacancy rate has fallen from 27% in 2016 to 8% in Q1 2026. In Q1 2026, only 48MW of capacity was delivered — well below the 2025 run rate.
The Savills framing matches what Armason sees in the market: the bottleneck is no longer capital or demand. It is the ability to get projects through the land, power, planning, and construction gauntlet simultaneously. That is an execution problem, not a market problem.
Source: Savills — Spotlight: UK Data Centre Building Capacity H1 2026
Ofgem reform is reshaping data centre strategy — whether developers are ready or not.
Multiple pieces of coverage this week examined the practical implications of Ofgem’s TMO4+ reforms for the data centre sector. The consistent message: the reform changes the competitive dynamics of grid access materially, and projects that have not yet secured land rights or planning consent are now at a structural disadvantage relative to those that have.
For data centre operators, the reforms could mean prioritisation for projects located in government-backed AI Growth Zones or aligned with national strategic energy plans. The reforms also introduce the possibility of ramped and flexible connection agreements, allowing operators to energise facilities in phases rather than waiting for full build-out — a potentially significant option for modular data centre deployments.
The connection between the Ofgem reform story and the Devon project is direct. Xlinks chose to bypass the grid queue entirely through private wire and on-site BESS. That is not an accident — it is the rational response of a developer who understands that the grid queue, even after reform, is not the fastest route to power for a project of this scale.
Sources: Computing — The New Race for Power: What Ofgem’s Grid Reform Means for Data Centres | Techerati — Data Centre Grid Connections Could Be Reshaped by Ofgem
The week in one line: A £12bn campus proposed for Devon farmland crystallises the geographic shift underway in UK data centre development, Savills confirms execution is now the market’s defining constraint, and Ofgem’s reform is reshaping grid access strategy for every project in the pipeline.